Third-party inspection of the ROC Concrete Weighbridge for the Thameside Energy Recovery Facility (ERF) Project. The scope included manufacturing quality verification, visual and dimensional inspections, and assessment of concrete surface conditions to ensure strict conformity with project specifications.
More Projects Like This
Similar inspection assignments from our portfolio.
345kV Insulator Strings — Type Test Witnessing
Type test witnessing for 345kV insulator strings — RIV, Corona and dielectric tests
400kV GIS Substation — FAT Witnessing
FAT witnessing for 400kV T155 GIS — endurance, dielectric and partial discharge testing
400kV GIS Substation — FAT Witnessing
400kV GIS FAT witnessing for AL DORA / AL FALLUJA substation project